Here’s a more detailed summary of the fastest-ever constructed metro station in India:
Location: Lucknow, Uttar Pradesh
Constructed by: Lucknow Metro Rail Corporation (LMRC)
Construction Started: 13 July 2017
Construction Completed: 22 February 2019
Time Taken: 19 months and 10 days
Commercial Operations Certified On: 23 February 2019
Corridor: Part of the 22.87 km-long North-South corridor of the Lucknow Metro
Metro Corridor Ends: At CCS Airport station, providing direct metro connectivity to the airport
This record showcases efficient project execution, strict adherence to timelines, and high-quality engineering.
The North-South Corridor connects key areas like Munshipulia, Hazratganj, Charbagh (the railway station), and terminates at the CCS Airport, significantly enhancing urban mobility.
The Commissioner of Metro Rail Safety (CMRS) clearance on 23 February 2019 allowed operations to begin almost immediately after completion.